A simple guide to complete installation
1. Test the cable first
2. Make the electric provisions as per instructions
3. Prime the subfloor using the primer and roller in the kit
4. Measure the room and mark out the cable spacing as detailed in the instructions
5. Layout out and tape down the cable
6. Test the cable
7. Fit the floor probe
8. Connect to the thermostat
9. Tile over the cable using flexible adhesive and grout
10. Wait at least two week before turning the heating system on for the first time.
A simple guide to complete installation
1. Test the cable first
2. Make the electrical provision as per instructions
3. Plan the start point and layout
4. Prime the sub-floor with the primer provided
5. Roll out the under tile mat, cutting the mesh in-between the looped cable when the opposite wall is reached
6. Peal the double sided tape of and stick the mat down
7. Fit the floor probe
8. Test the cable again
9. Tile over using flexible adhesives and grout